RIBA Stages of Work: A Comprehensive Overview of the 8 Steps

12 min read
Oct '25 • by James Henry

Quick summary

The RIBA plan of work organises building projects into eight stages, from initial idea to ongoing use, with each step focusing on specific tasks like briefing, designing, construction, and operation. It ensures clear progress and communication, helping teams deliver projects efficiently and on time, covering everything from strategic definition to post-occupancy evaluation.

The Royal Institute of British Architects (RIBA) Plan of Work is the definitive model for the design and construction process in Great Britain. First conceived in 1963, it has evolved over the decades to reflect changing industry practices and requirements. The latest version of the RIBA stages organises the process of briefing, designing, constructing, maintaining, operating and using buildings into eight distinct phases. This comprehensive framework provides guidance for all disciplines involved in construction projects, and serves as the basis for developing detailed professional services and building contracts.

Let's have a look at everything in detail, starting with Phase 0.

The Eight Stages of the RIBA Plan of Work

Stage 0: Strategic Definition

The primary aim of Stage 0 is to determine if a building project is the best solution to meet the client's requirements. This stage involves developing a Business Case that examines different options for achieving the Client Requirements, considering Project Risks and the Project Budget for each possibility.

Key tasks during Stage 0 include:

  • Preparing Client Requirements
  • Developing the Business Case for feasible options
  • Ratifying the option that best delivers Client Requirements
  • Reviewing Feedback from previous projects
  • Undertaking Site Appraisals

No design team is required at this stage. The client may appoint advisers to provide strategic guidance.

Additional considerations during Stage 0 include:

  • Assessing the client's experience with building projects
  • Determining the client's financial capacity and willingness to fund the project
  • Identifying the status and authority of the client representative, especially in cases involving multiple stakeholders
  • Understanding whether the project is for direct occupation or speculative development
  • Considering the potential involvement of third parties who may need to be consulted
  • Evaluating the project's alignment with the client's broader business or organisational goals

It's crucial during this stage to keep thorough records of all communications and decisions made. This documentation will serve as a valuable reference point as the project progresses through subsequent stages.

Whilst no formal design work takes place in Stage 0, it's an opportune time to consider the potential implementation of Building Information Modelling (BIM) and other digital technologies that could benefit the project in later stages.

By thoroughly addressing these elements in Stage 0, clients can ensure they have a solid foundation for their project, minimising the risk of costly changes or misalignments in later stages.

Stage 1: Preparation and Briefing

If a building project is determined to be the best way forward, Stage 1 focuses on developing a detailed Project Brief. This captures the client's requirements in terms of Project Outcomes, Quality Aspirations and Spatial Requirements.

Key activities during Stage 1 include:

  • Preparing the Project Brief
  • Undertaking Feasibility Studies
  • Agreeing the Project Budget
  • Sourcing Site Information and Surveys
  • Preparing the Project Programme and Project Execution Plan

Additional important tasks in this stage involve:

  • Reviewing the scope of work and assessing office resources
  • Identifying the client representative and authorised agents
  • Advising the client on statutory and legal obligations, including planning approvals and health and safety legislation
  • Establishing procedures for client sign-offs and approvals
  • Considering the project's risk profile and procurement options
  • Setting up project administration procedures and quality management systems
  • Identifying the need for specialist consultants and their roles
  • Undertaking initial site visits and collating contextual material
  • Checking for potential site contamination or hazardous substances

While a full design team is typically not appointed yet, the client may use advisers to assist with brief development and design team selection. It's crucial to establish clear communication channels and reporting procedures between the client's representative and any appointed consultants.

If Building Information Modelling (BIM) is to be implemented, this stage may involve appointing an information manager and defining BIM protocols and responsibilities.

By thoroughly addressing these elements in Stage 1, clients can ensure a solid foundation for the project, minimising the risk of costly changes or misalignments in later stages.

Stage 2: Concept Design

Stage 2 marks the start of the design process proper. The design team is appointed and develops an Architectural Concept incorporating Strategic Engineering requirements. This concept is tested against the Project Brief through Design Reviews with the client.

Core Tasks

  1. Preparing the Architectural Concept
  2. Incorporating Strategic Engineering requirements
  3. Aligning the design to the Cost Plan, Project Strategies and Outline Specification
  4. Agreeing Project Brief Derogations
  5. Undertaking Design Reviews
  6. Preparing the Stage Design Programme

Additional Activities

During this stage, the project team will also:

Review and Develop:

Initial Project Brief into the final Project Brief
Procurement and Construction Strategies
Project Execution Plan and Health and Safety Strategy

Prepare and Coordinate:

  • Responsibility Matrix for design team members
  • Outline Specification
  • Information from cost consultants and specialists

Advise the Client:

  • On appointing further consultants and specialists
  • Regarding the Plan for Use Strategy, including handovers and commissioning

Maintain:

  • Careful records of all conversations, consultations, and design team meetings
  • Regular communication with the client, including cost reporting

BIM Integration (if applicable)

If using Building Information Modelling:

  • Organise initial model sharing for strategic analysis
  • Identify key BIM elements and create concept-level parametric objects Assist in integrating data from contractors and suppliers

By thoroughly addressing these elements in Stage 2, the project team can ensure a solid conceptual foundation for the design, aligning it with the client's requirements and project constraints. The stage concludes with obtaining client approval to proceed to Stage 3.

cosy home

Stage 3: Spatial Coordination

Stage 3 focuses on testing and validating the Architectural Concept to ensure the design is Spatially Coordinated before detailed technical design begins. This stage is crucial for aligning the design with project constraints and client expectations.

Key activities during Stage 3 include:

  1. Undertaking Design Studies and Engineering Analysis
  2. Performing Cost Exercises to test the Architectural Concept
  3. Producing a Spatially Coordinated design
  4. Initiating Change Control Procedures
  5. Preparing and submitting the Planning Application

Throughout this stage, the project team works to refine and coordinate various aspects of the design. This involves integrating input from all design team members and specialists, ensuring that structural, mechanical, and other systems work harmoniously within the architectural vision.

Cost considerations play a vital role. The team develops an elemental Cost Plan, followed by a firm Cost Plan with cash flow forecast. Regular discussions about the impact of design decisions on cost allocations help maintain alignment with the project budget.

Client engagement remains crucial. The team should:

  • Confirm client acceptance of the Stage 2 Architectural Concept
  • Review and develop the Project Brief
  • Advise on appointing additional consultants or specialists as needed
  • Alert the client to any issues raised by statutory bodies

If using Building Information Modelling (BIM), the model becomes a central tool for design development and coordination. It can be used for environmental performance analysis, area calculations, and integrating data from various team members.

The stage concludes with finalising the Spatially Coordinated design and obtaining client sign-off. This sets the stage for the detailed technical design phase to follow, with a well-coordinated spatial design that balances the client's requirements, budget constraints, and project strategies.

Contents

We'll take you on a journey through the RIBA Plan of Work, breaking down each stage to help you understand the key activities and milestones in bringing a building project to life - from initial concept to long-term use. If you'd like to skip ahead, simply click the RIBA stage you're interested in:

Stage 0: Strategic Definition
Stage 1: Preparation and Briefing
Stage 2: Concept Design
Stage 3: Spatial Coordination
Stage 4: Technical Design
Stage 5: Manufacturing and Construction
Stage 6: Handover
Stage 7: Use
Key Aspects of the RIBA Stages
Conclusion